Search This Blog

Showing posts with label Dredging. Show all posts
Showing posts with label Dredging. Show all posts

Thursday, June 09, 2011

EPA Announces the Second Phase of Historic Hudson River Cleanup Underway

Lakes Entrance Dredger April HamerImage via Wikipedia (Glens Falls, N.Y. – June 6, 2011) The U.S. Environmental Protection Agency (EPA) today announced that the dredging of sediment contaminated with polychlorinated biphenyls (PCBs) has resumed in the Upper Hudson River, marking the start of the second and final phase of the Hudson River cleanup.  The historic dredging project targets approximately 2.4 million cubic yards of PCB-contaminated sediment from a forty-mile section of the Upper Hudson River between Fort Edward and Troy, NY.  PCBs are potentially cancer-causing in people and build up in the fat of fish and mammals, increasing in concentration as they move up the food chain.  The primary risk to humans is the accumulation of PCBs in the body from eating contaminated fish.  General Electric (GE) is conducting the cleanup work with EPA oversight, under an agreement with the Agency.  This final phase of the cleanup project is expected to take five to seven years to complete.

During the 2011 dredging season, mechanical dredges will collect buckets of PCB-contaminated sediment from a 1.5-mile stretch of river just south of the town of Fort Edward.  Four to six dredges will work 24 hours a day, six days a week through the summer and fall to remove approximately 350,000 cubic yards of PCB-contaminated sediment from 100 acres of river bottom.  Dredging will begin in the western channel of Roger’s Island and move south in the main stem of the river.  Between 1947 and 1977, an estimated 1.3 million pounds of PCBs were discharged into the river from two GE capacitor manufacturing plants located in Fort Edward and Hudson FallsInformation about the Hudson River PCBs Superfund site can be found at http://www.epa.gov/hudson.

People seeking general information about the project are encouraged to contact Larisa Romanowski at (518) 747-4389; romanowski.larisa@epa.gov.   Residents who have questions or concerns related to dredging operations should call GE’s 24-hour dredging information phone line at (518) 792-4087, or, toll-free (888) 596-3655.
Enhanced by Zemanta

Tuesday, April 06, 2010

EPA Submits Final Report on First Phase of Hudson River Dredging

This image comes from the Swedish encyclopedia...Image via Wikipedia
On March 8, 2010, the Environmental Protection Agency (EPA) released a detailed technical assessment of the first phase of the dredging operations on the polychlorinated biphenyl (PCB)-contaminated sediment in the upper Hudson River.  This assessment, along with General Electric's assessment, are being submitted to the panel of independent scientific experts for review.  In addition, to the report being submitted to the scientific panel, EPA is also soliciting comments from the public that will also be submitted to the panel.  The first phase of this project is being used as a test run for the far larger phase 2 of this project, which EPA hopes to start in 2011.  The technical report is 185 pages and covers a number of operations and discusses problems and recommended changes to reduce PCB air emissions and water resuspensions.  Needless to say EPA feels that the operation can be done successfully with a few changes and GE has some major issues with the process because of the PCB resusensions.  It will be interesting to see what the panel has to say.
Reblog this post [with Zemanta]

Wednesday, January 27, 2010

Wall Street Journal Reports on PCB Dredging Operations

Hudson River watershedImage via Wikipedia
On December 7, 2009 we wrote about the dredging operations on the Hudson River (http://futureenv.blogspot.com/2009/12/hudson-river-pcb-dredging-good-bad-ugly.html).  On January 21, 2010 the Wall Street Journal reported that higher PCB levels were found during the Hudson River dredging operations.  Both General Electric and the EPA released draft evaluations of the project.  Both reports found higher levels of PCBs than originally anticipated, putting into question the performance standards for the project.
Reblog this post [with Zemanta]

Monday, December 07, 2009

Hudson River PCB Dredging – the Good, the Bad, & the Ugly

Bear Mountain Bridge from the top of Bear Moun...Image via Wikipedia
On May 15, 2009, the Environmental Protection Agency (EPA) announced the start of dredging operations on the upper Hudson River. The goal of this project is to remove approximately 113,000 kilograms of polychlorinated biphenyls (PCBs) from the river by 2015. General Electric Company’s (GE) Fort Edward and Hudson Falls plants legally released the PCBs into the river from 1944-1997. GE is conducting the dredging and related work under the terms of a November 2006 consent decree, after EPA ordered GE to dredge the tainted sediment from the river and dispose of it. The Hudson River covering a 200 mile stretch is the largest superfund site in the United States.
The Good – the ultimate goal of this dredging operation is to restore the health of the river, to enhance regional tourism and commercial opportunities, and improve commercial and recreational fishing in the Hudson River between Fort Edward and Albany currently prevented by the PCB contamination. The Hudson River dredging plan is based on a previous successful PCB dredging project along Lake Champlain in Plattsburgh, NY. The plan includes daily water sampling downstream from the dredging operations, these sampling results must average below 500 parts per trillion of PCBs, which is the same as the drinking water standard, for dredging operations to continue. On August 5, 2009 dredging operations stopped because sampling results exceeded the standard. A review of the operations called for enhanced engineering controls. The enhanced engineering controls allowed dredging operations to resume on August 11, 2009. There have been no reported problems since.
The Bad – transporting the PCB sediment to its eventual resting place in Texas will take a 2,000 mile trip through a number of states. The PCB-sediment will be dewatered in Fort Edward packed onto a 81-car train and tightly wrapped in heavy-duty plastic. EPA deemed rail travel as the safest method of transporting the soil. The national rail traffic will determine the ultimate route of the train and it will take about five days to get to Texas. The Lone Star Chapter of the Sierra Club notes in their release dated February 11, 2009, “that an environmental impact statement has not been prepared for the proposed rail shipment. The shipment poses a potential for serious accident hazards in or near dozens of urban areas and states through which trains would pass. One major rail accident could lead to a catastrophic contamination event if drums were breached and highly concentrated PCBs were released.” According to The Saratogian article “Hudson River PCBs en route to West Texas”; the Federal Railroad Administration’s safety data, 726 accidents involving trains carrying hazardous materials occurred in 2008, more than half of those in the rail yard. Everything from a slight bump in a rail yard to a major derailment qualifies as an “accident” in that report. Examples of the type of derailments covered by the report include, the 2 that occurred within 24-hours of each other on September 26 & 27, 2009 in Montana and Wyoming. These derailments involved minimal spillage and the cars remained erect. While other derailments like the one that occurred on January 22, 2002 that caused a toxic cloud of anhydrous ammonia near the town of Minot in North Dakota, still have an effect on the people who live there, even years later. That derailment required the digging up of 97,000 tons of contaminated soil and 25,000 square feet of river ice and more than 1,000 people affected according to USA Today. An Environmental Impact Statement would at least look at the possible consequences of a derailment and try to anticipate a derailment that would be catastrophic.
The Ugly – the final resting place for the estimated 2.65 million cubic feet of PCB-contaminated sediment is Waste Control Specialists (WCS) in Andrews, Texas. Rural Andrews County, Texas is a desolate desert county just over the New Mexico border and consists of 1500 square miles and a population of about 14,000 people. Andrews, the only incorporated city in the county, has a history more than a decade long of hazardous waste disposal. A study commissioned by the town and performed by the professors at Texas Tech University determined that hazardous waste disposal was a suitable industry for the city and county, because the red-bed clay found there is a natural impermeable liner and the area where WCS located their site does not overlap the Ogallala Aquifer. WCS as an EPA permitted toxic waste facility accepted the first load of PCB sediment on June 28, 2009. Prompting a backlash, from the people in the area, regarding the feasibility of dumping the PCB-contaminated sediment at the WCS facility. The Lone Star Chapter of the Sierra Club wrote a letter to the EPA Administrator Lisa Jackson urging a halt to the shipping of the PCB wastes to Texas. Is it a case of “not in my backyard” (NIMBYism)? Maybe not, there seems to be a disagreement on whether the WCS facility is over or close enough to the Ogallala Aquifer (a sensitive underground water resource). The claims range from 14 feet to 500 feet to the nearest water table. The Ogallala Aquifer stretches from South Dakota to Texas and is the largest aquifer in North America. It seems that the concerns of the Lone Star Chapter of the Sierra Club may be justified. It seems that EPA should have checked to make sure how close this waste facility actually was to the Aquifer.
Like all hazardous material/waste situations, cleaning up the problem brings up many questions some good, some bad, and some downright ugly. However, if we ask the questions and we look at the problems carefully and thoroughly, we can eventually solve these problems to the satisfaction of all concerned and involved.
Reblog this post [with Zemanta]

That Time of Year! Conferences, Posting Requirements, and OSHA Violations Increased!

It's that time of year again. We're between conferences.  February 15-16, 2024 was the Professional Abatement Contractors of New Yor...